Rapid response to a major utility outage
Location:
Oxford, UK Project type:
Product Hire Sector:
Utilities When a major utility outage occurred in the south of England, requiring 7.5mVA of temporary 11kV power, we received a call requesting emergency power support.
Woodlands deployed 3 x 1250kVA and 2 x 1800kVA packages to site with full engineering support, supplying generator technicians and HV engineers. The gensets were supplied in sound attenuated containers, to comply with noise regulations on site.
Within 4 hours of the initial call, we were able to deliver the first equipment on site.